The City of Taylor started construction on Beech Daly Road between Eureka and Pennsylvania last Friday (May 9).  

Here is a tentative schedule of where the project stands.  Obviously, this is all weather dependent, and the plan is already behind from this week's rain:
  • May 14 to May 16: Concrete patching and curing
  • May 19 to May :21 Joint work and prep for paving
  • May 22: Fabric placement
  • May 23: Leveling course asphalt

Following the leveling, the contractor will mobilize to mill the other lane of the road and swap sides.

Please note that driveways will be maintained during construction. However there may be times they will be inaccessible.  